How much large solar is operating or in the pipeline in Mid-Western?

1,378

MW of large solar farms operating or in the pipeline

NSW council area · 8,752 km²

  • 66 to 132 kV
  • 220 to 275 kV
  • 330 kV
  • 500 kV
  • Operating solar farm
  • In the pipeline
  • Approximate location (postcode or referral area centre)
  • EPBC referral area
Fig. 1 · Solar farms in Mid-Western · AEMO, CER, DCCEEW EPBC referrals, Geoscience Australia · Councils ABS 2025 · 4 Oct 2026 · Basemap and farm outlines © OpenStreetMap contributors
Operating
778 MW
In the pipeline
600 MW
Solar farms
5

Source AEMO, CER, DCCEEW EPBC referrals, Geoscience Australia · 4 Oct 2026

Solar farms

Solar farms in Mid-Western, NSW
Solar farmStatusCapacity
Birriwa Hybrid (approximate location)Proposed600 MW
Stubbo Solar Farm (approximate location)Operating400 MW
Wollar Solar FarmOperating280 MW
Beryl Solar FarmOperating98 MW
Proposed large-scale solar farm project (approximate location)ProposedNot published

Source Geoscience Australia · 66 kV and above · From the area's centre

Nearest substations

Substations nearest the centre of Mid-Western, NSW
SubstationVoltageDistance from area centre
Mudgee132 kV16 km
Wollar West330 kV28 km
Wollar500 kV28 km

Source Global Solar Atlas 2.0, Solargis · Mean of 12,095 cells of about 1 km

Average solar yield

1,655 kWh per kWp a year

Yield higher than 12% of Australia’s land

Questions

What counts as in the pipeline?

In the pipeline is every farm that is commissioning, committed, anticipated or proposed (publicly announced, or referred for approval). The headline adds those to every operating farm. Withdrawn projects are not counted. A farm with no published capacity is listed but adds no MW. A farm placed at the centre of its postcode or EPBC referral area, because no source gives its own location, counts in the council area that point falls in. Here: 778 MW operating across 3 farms, 600 MW in the pipeline across 2.

What do committed and anticipated mean?

They are AEMO's stages in its Generation Information. Committed: the project has known timing and satisfies all five of AEMO's commitment criteria, or four of them with the planning or contracts criterion partly met. Anticipated: it is sufficiently progressed towards meeting at least three of the five. Publicly announced: announced, but not yet far enough along to be anticipated or committed.

Where does the data come from?

Solar farms: AEMO under its copyright permissions, with attribution; the Clean Energy Regulator (CER) under CC BY 4.0; EPBC referrals from the Department of Climate Change, Energy, the Environment and Water (DCCEEW) under CC BY 4.0; Geoscience Australia under CC BY 4.0. Each farm is placed in the council area its point falls in, using the ABS 2025 council boundaries (CC BY 4.0). Substations: Geoscience Australia's electricity infrastructure layer (CC BY 4.0), operational substations of 66 kV and above. The substation distances are straight lines from the centre of the council area, not from any farm.

Why do some farms say approximate location?

3 farms are placed at the centre of their postcode or EPBC referral area, because no source gives their own location, so their council area is approximate. They count in the headline.

Why is a solar farm I know missing?

A farm appears here only once a public source gives its location. The sources for this area are AEMO, CER, DCCEEW EPBC referrals, Geoscience Australia. Large solar farms are grid-scale power stations. Rooftop solar is not counted.

Which of these farms also farm the land?

Agrivoltaics means farming the same land as a solar farm, usually grazing sheep under the panels. No public source found so far says sheep, cattle or crops are on site at a farm in this area. That means nothing was found, not that there is no grazing.